Q1. A can finish a work in 40 days and B in 60 days. In how many days will they finish it working together?

  1. 23 days
  2. 26 days
  3. 24 days
  4. 20 days

Answer: C. 24 days

Together they do 1/40 + 1/60 = 1/24 of the work per day, so they need 24 days.

Q2. Pipe A fills a tank in 3 hours and pipe B empties it in 4 hours. If both are opened together, how long will the empty tank take to fill?

  1. 1.71 hours
  2. 7 hours
  3. 1 hours
  4. 12 hours

Answer: D. 12 hours

Net filling per hour = 1/3 − 1/4 = 1/12 of the tank, so it fills in 12 hours.

Q3. A alone can do a job in 12 days. A and B together can do it in 8 days. How long will B alone take?

  1. 4 days
  2. 24 days
  3. 28 days
  4. 20 days

Answer: B. 24 days

B's one-day work = 1/8 − 1/12 = 1/24, so B alone takes 24 days.

Q4. A can finish a work in 20 days and B in 30 days. In how many days will they finish it working together?

  1. 11 days
  2. 12 days
  3. 10 days
  4. 14 days

Answer: B. 12 days

Together they do 1/20 + 1/30 = 1/12 of the work per day, so they need 12 days.

Q5. Pipe A fills a tank in 5 hours and pipe B empties it in 6 hours. If both are opened together, how long will the empty tank take to fill?

  1. 30 hours
  2. 11 hours
  3. 32 hours
  4. 1 hours

Answer: A. 30 hours

Net filling per hour = 1/5 − 1/6 = 1/30 of the tank, so it fills in 30 hours.

Q6. A alone can do a job in 30 days. A and B together can do it in 20 days. How long will B alone take?

  1. 10 days
  2. 12 days
  3. 50 days
  4. 60 days

Answer: D. 60 days

B's one-day work = 1/20 − 1/30 = 1/60, so B alone takes 60 days.

Q7. A can finish a work in 28 days and B in 21 days. In how many days will they finish it working together?

  1. 14 days
  2. 7 days
  3. 24.5 days
  4. 12 days

Answer: D. 12 days

Together they do 1/28 + 1/21 = 1/12 of the work per day, so they need 12 days.

Q8. Pipe A fills a tank in 4 hours and pipe B empties it in 6 hours. If both are opened together, how long will the empty tank take to fill?

  1. 2 hours
  2. 2.4 hours
  3. 12 hours
  4. 14 hours

Answer: C. 12 hours

Net filling per hour = 1/4 − 1/6 = 1/12 of the tank, so it fills in 12 hours.

Q9. A alone can do a job in 15 days. A and B together can do it in 10 days. How long will B alone take?

  1. 6 days
  2. 30 days
  3. 34 days
  4. 25 days

Answer: B. 30 days

B's one-day work = 1/10 − 1/15 = 1/30, so B alone takes 30 days.

Q10. A can finish a work in 30 days and B in 60 days. In how many days will they finish it working together?

  1. 30 days
  2. 20 days
  3. 19 days
  4. 45 days

Answer: B. 20 days

Together they do 1/30 + 1/60 = 1/20 of the work per day, so they need 20 days.

Q11. Pipe A fills a tank in 10 hours and pipe B empties it in 15 hours. If both are opened together, how long will the empty tank take to fill?

  1. 5 hours
  2. 6 hours
  3. 25 hours
  4. 30 hours

Answer: D. 30 hours

Net filling per hour = 1/10 − 1/15 = 1/30 of the tank, so it fills in 30 hours.

Q12. A alone can do a job in 18 days. A and B together can do it in 12 days. How long will B alone take?

  1. 36 days
  2. 40 days
  3. 30 days
  4. 7.2 days

Answer: A. 36 days

B's one-day work = 1/12 − 1/18 = 1/36, so B alone takes 36 days.